Example: Establish The Assignment (AST) |
|
Relationships
Description
Main Description |
Preconditions
-
Master test plan - The master test plan drives the setup and execution of the test level.
-
Milestones - Often, as soon as the test assignment is issued, a number of milestones are established, such as the
delivery date of the test basis, the test object, infrastructure and the date of going into production.
-
Available resources - The client often sets limits to the available people, resources and budget.
-
Norms and standards to be maintained - From within the (test) organisation or the master test plan, certain
requirements may be set as regards method of operation, procedures, techniques, templates, etc.
Assumptions
-
Quality of preceding tests - The preceding tests, e.g. development or system tests are carried out in the agreed
manner.
-
Quality of test object - The test object has the agreed entry quality. This should be established with the aid of
so-called entry criteria, which overlap with (but are not necessarily the same as) the exit criteria of the
preceding test.
-
Support to be supplied - Within the test process there is a need for various forms of support,
e.g. in respect of the test basis, test object, domain knowledge and/or infrastructure. This support may be
required to a certain degree and/or for a certain period. Bear in mind, for example, the availability of developers
for solving obstructive defects during the test execution. Usually, each test level has its own expertise. For
instance, the users acceptance test will have little need of domain knowledge support, while the support needs will
concern precisely the other types of expertise, such as technical or testmethod support.
-
Changes in test basis and test object - The test team should be involved in the implementation of changes. In most
cases, this simply means following up the existing procedures within the system development process. For example,
the test manager should participate in the Change Control Board in order to estimate the consequences of a change
from the test point of view.
-
Delivery of the test object - The development team delivers the test object in a number of different but
efficiently testable parts, and takes responsibility for installation in the test environment.
-
Reaction time to defects - How quickly should the project react to the finding of defects. Below is an example of
such agreements:
Severity
|
Priority
|
Reaction time
|
Lead time
|
Test-obstructive
|
High
|
1 hour
|
4 hours
|
Severe defect
|
High
|
1 hour
|
1 working day
|
Regular defect
|
High
|
1 working day
|
2 working days
|
Regular defect
|
Low
|
1 working day
|
To be determined per
defect
|
Cosmetic defect
|
Low
|
2 working days
|
To be determined per
defect
|
|
Copyright
© 2006, Sogeti Nederland B.V. All rights
reserved.
|
|